Hi!Hi all,
I have just got off the phone to Mr Islam Erfan (Marketing manager)
I was discussing with him the delay of our apartments and the reasons for such a delay, and what compensation we can expect.
Firstly, the reason he believes the reason for the delay is some part of the construction companies fault in Marsa Alam and partly their bad management.
Secondly, as for compensation, they are in discussions about this, I asked when they may know an answer and he stated may be by the end of the year!
As for a completion date he has said April 2010, maybe beging of April but his honest opinion end of April. Personally I think maybe in May.
I hope this answers some questions.
Deano.
According to reseved mail from Mr. Tarek in Sharm El Sheikh real estate we shall have compensation.
But thats at the handover. What we should have in mind is that we must stand together on this. Its not a "discussion" about our compensation ! We demand a compensation according to our contracts!
I was wondering how many in this forum has bought in block 12 and 13 with handover 31-3-2009?
Best regards Geir Moen.